his service is earned out against the hidden enemy of Human being. Termites which are social insects line in the Earth more than 250 million years, long before the existence of human being. They are broadly classified into three group”s- i.e. subterranean Termites, Damp, Wood Termite and Dry Wood Termites. Out of these three groups the Subterranean Termites causes maximum DFamages in the world. They feed on anything which carries Cellulose i.e. Wood, Paper, Clothes etc and causes significant Aesthetic damage to the property.
The treatment consists of Drill-Inject-Seal Technique to form a chemical barrier against termites around your Property. This treatment can be carried out in building during construction (Pre-construction Service) and also to the existing Building (Post Construction Service), the Service is backed by Annual Maintenace Contract(AMC) / Five years Maintenance Contract/ Ten Years Maintenance Contract Warranty against termites.
Service Categories
Termicon Services
RatCon Solutions
BugCon Services
WoodborerCon Services
FlyCon Services
MosquitoCon Service
FumiCon Services
Housekeeping Services
Security Guards Services
Disinfection Services
Pre Construction TermiCon Services – As IS 6313 PartII
A - TREATMENT OF SOIL
The chemical emulsion of Termiticides as per BIS:6313 (Part 2) : 2013 shall be applied uniformly at the prescribed rate in all the stages to creating the continuous chemical barrier to the soil before laying soling and plain cement concrete (PCC). The treatment shall be carried out in the following stages:-
Treatment of top Surface of Plinth Filling
Treatment at Junction of Wall and Floor
Treatment of Soil along External Perimeter of Building
Sub soil area (except plinth area
Treatment of sidewalls by spraying pesticide
B- TREATMENT OF WOODWORK OF ALL FLOORS
Treatment of door & window frames
Treatment of wood work, board & ply board
Treatment of walls
C- OPTIONAL – TERMITUBE SYSTEM
Termitube installation will be completed at flooring level, will be tested in the presence of your representative and the duly completed structure will be handed over to you by fixing the Junction Box, which could be opened, used for periodic recharging of Termiticides in future.
Installation of Termitube System:
After levelling of soil within plinth area of building, 100 x 100 mm channel in a grid way will be made with the help of gaiti along with plinth walls.
Laying the Termitube by using jointers in the channels all along the plinth walls (both sides).
Levelling by filling the sand in the channels.
After this step, sand-bed or PCC can be done by your civil contractors.
Testing of Termitube System by injecting the chemical emulsion with the help of motorised spray pump wiill be carried out 2 times (before and after PCC or send-bed work.
Junction box will be fixed as per the layout plan of building with permission of architect or client.